Notice: Undefined index: HTTP_ACCEPT_LANGUAGE in /mnt/volume_sgp1_04/busine23n9s5der/public_html/common/config.php on line 14
Padma Bridge’s 34th span installed, making over 5.1km visible

Dhaka, Wednesday


25 December 2024


Business Insider Bangladesh

Padma Bridge’s 34th span installed, making over 5.1km visible

|| BusinessInsider

Published: 21:53, 25 October 2020  
Padma Bridge’s 34th span installed, making over 5.1km visible

File photo

Padma Bridge’s 34th span installed, making over 5.1km visible

BI Report

Dhaka (Oct 25, 2020): The 34th span of the Padma Bridge was installed today, bringing a total of over 5.1 kilometers of the structure into view.

The span number ‘2A’ was installed between seven and eight No. pillars at Mawa point, six days after the last one was set up.

Executive Engineer (Bridge) Dewan Md Abdul Quader confirmed the matter and said around 4:00pm on Saturday, a crane ship started work to lay span on the pillars from the Mawa construction jetty, but it was too dark to work smoothly when it reached near the pillars.

That’s why, work of span installation is completed today morning, he added.

With the new one, a total of three spans have been placed on the bridge this month.

The 35th span is to be set up on the banks of Padma river in Mawa on October 30. The other 6 spans will be installed on the pillars by December this year.

A total of 42 pillars are being constructed for the 6.15 km long two-storey Padma Bridge.

Of these, 21 will be at Mawa and 21 at Jazira. A total of 41 spans will sit on these 42 pillars.

Construction of the Padma Bridge began in December 2014. The Padma Bridge became visible on September 30, 2017 with the installation of the first span on poles 36 and 37.

China Major Bridge Engineering Company (MBEC) is working on the main bridge, and Sino Hydro Corporation is working on river management.

Abdul Momen Limited has constructed two connecting roads and infrastructure.

The Padma Bridge is expected to be opened in 2021.